Kilkenny County Council is to be commended for its preparation of a Wind Energy Development Strategy as laid out in Appendix K.  This provides a plan-led, supportive policy framework for the wind energy industry to bring forward planning applications for developments of appropriate scales in appropriate locations and forms an integral part of the Draft CDP.

In preparing a new Wind Energy Strategy (WES) for County Kilkenny as part of the preparation of the Kilkenny County Development Plan 2021-2027, Kilkenny County Council is again to be commended for taking the opportunity to review its renewable energy policies at the start of a new decade, in light of quite different Government, climate change, environmental and energy policies and bearing in mind the 76 MW currently operational in Co. Kilkenny. The final Kilkenny CDP will inform the policies and ambitions of the county for a crucial decade in our decarbonisation journey and will be integral in the successful development of renewable energy capacity.

Changes to various Government renewable energy policies in recent years has now put planning permission as the critical first stage of any renewable energy projects. Only when planning permission is secured can a project now apply for a grid connection to export the energy to the national electricity grid and identify a route to market to sell the power. Therefore, clear and supportive planning policies for wind and all renewable energy developments are required to ensure we meet the challenges of addressing climate change and decarbonising the Irish economy over the next decade.

With County Kilkenny’s significant area and good wind energy resource, County Kilkenny needs a progressive and ambitious Wind Energy Strategy (WES) with clear and supportive policies in favour of further wind energy development.

RWE welcomes the approach in relation to the proposed new Wind Energy Development Guidelines (due to be finalised later this year) and that the final CDP and WES for County Kilkenny refers to these Guidelines and require future proposed wind energy developments in County Kilkenny to comply with the guidelines of the day. The Department has clearly stated on numerous occasions the 2006 guidelines remain in effect until they are replaced.

RWE would ask Kilkenny County Council to remove any extracts from the draft Wind Energy Development Guidelines (2019) from the final plan in anticipation of the final published guidelines this year.

Large Wind Energy Developments in ‘Open to Consideration’ Areas

RWE commend Kilkenny County Council on the complete designation of Co. Kilkenny under the three proposed Wind Energy Strategy Areas in table 11.3 of the WES as outlined in Appendix K. This provides a very clear methodology applied to reach the three strategy areas for the county as ‘Acceptable in Principle, ‘Open to Consideration’ and ‘Not Normally Permissible’. RWE note that Large Scale Wind Energy Developments of greater than 5MW will only be considered in areas designated as ‘Acceptable in Principle’.

“The rationale behind this policy is to minimise the visual impacts of such large-scale developments, in addition to effects on the environment of County Kilkenny as a whole, as well as to facilitate appropriate grid connections. These will be assessed in accordance with the Wind Energy Development Guidelines.”

RWE would ask Kilkenny County Council to consider Large Scale Wind Energy Developments in areas designated as ‘Open to Consideration’ as well. This areas is, “characterised by no significant conflict with environmental designations or sensitivities.” The rationale put forward by Kilkenny County Council for restricting Large Scale Wind Energy Developments to areas designated as ‘Acceptable in Principle’ relate to the potential effects on the environment, access to the national grid system and potential visual impacts.

Areas designated as ‘Open to Consideration’ are defined as having, “no significant conflict with environmental designations or sensitivities” as outlined in Appendix K. Existing or planned electricity grid capacity should not be considered a constraint for the purposes of determining whether areas of County Kilkenny are suitable or unsuitable for wind energy development. Grid capacity is a technical and electrical engineering constraint and is not an appropriate constraint when identifying potential areas for wind energy development. Finally, as laid out in the RES, all large scale wind energy developments would be subject to a detailed Environmental Impact Assessment, including a visual impact assessment. RWE would argue that, for the reasons mentioned above,  large scale wind energy developments should be given consideration in areas designated as ‘Open to Consideration’ where otherwise appropriate.

Designating Sufficient Lands to meet 2030 Targets and Beyond

RWE note that 50,000 ha of land is contained in the strategy area ‘Acceptable in Principle’ which is the equivalent of 24% of the entire county containing potential lands for wind energy developments. RWE do not necessarily agree with Kilkenny County Council’s statement, “that a typical wind turbine requires a land take of 0.4 hectares, (and) it is clear that notwithstanding the 500m setback criteria from residences, this Strategy provides for sufficient land area.”  

RWE have looked at this 50,000 ha from a wind farm development perspective. Considering the WEDGs, a 500m buffer from all houses was applied using a geodirectory database. A 3.5 rotor diameter exclusion from 110kV overhead lines was applied as per Eirgrid specifications. A rotor diameter of 130m was used, which RWE feel is a conservative representation of turbine specifications going forward. Any Natura 2000 sites were then excluded, including Special Protected Areas and Special Areas of Conservation. This reduced the amount of potentially available land to approximately 6,100 ha. All operational wind farms were located on the SEAI Wind Atlas and excluded, leaving 5,750 ha. A commercially viable wind farm would need to be 20 MW at a minimum. A four turbine wind farm of 5MW turbines was considered. A typical wind turbine requires a land take of 0.4 ha for the constructed hardstand, however there is a considerable area needed between turbines to optimise the wind take. A conservative measure of 4 rotor diameters was used in this example. This means that an area of 21 ha is needed around a turbine, with 85 ha for a 20 MW wind farm.

Considering an area of 85 ha is needed for a wind farm of 20 MW, the 5,750 ha available allows for 67 wind farms of 20MW, or 1.3 GW. However, there is a very high attrition rate applied to wind farm development. There are numerous constraints which could result in a potential wind farm development being unsuccessful. Industry best practice would suggest an 80% attrition rate, equating to 270 MW available in the areas designated as ‘Acceptable in Principle’ overall.

It is worth noting that tip heights are increasing as turbine technology improves, resulting in fewer numbers of larger turbines in wind farms. In recent years, wind farm planning application consents are frequently granting maximum tip heights of 150 – 185m tip heights to avail of more efficient turbine models. If this same example uses a tip height of 150m, 110MW of land is available. This considers a 600m setback from houses as per the draft Wind Energy Development Guidelines (2019), which is expected to be published imminently. These figures serve to highlight the importance of designating a sufficient quantum of land for potential wind energy development.